
PROPOSED ENERGY PROJECTS
In 2015, Hawai‘i enacted a law that requires electric utility companies to sell only renewable energy to their customers by 2045 (Act 97) — the first such mandate in the United States.
PROPOSED PROJECTS
Hawaiian Electric uses a competitive bidding process to secure new large-scale renewable energy projects. In this process, developers or independent power producers—companies that design, build, and operate renewable energy facilities—submit proposals to meet specific system needs identified by Hawaiian Electric in the grid planning process.
The procurement process applies only to Hawaiian Electric’s service areas on O’ahu, Maui, and Hawai’i Island, and describes the procurement of large-scale renewable energy projects on these islands. Other islands follow different processes, with Moloka’i and Lāna‘i addressed separately in Docket No. 2019-0178 and Kaua’i addressed separately by its utility, Kauai Island Utility Cooperative.
The projects shown below are generally part of the Stage 2 or 3 Hawaiian Electric Competitive Procurement. Information on this procurement can be found in Docket 2017-0352.
PROJECTS PROPOSED FOR DEVELOPMENT AND IN DEVELOPMENT (BY ISLAND AND ESTIMATED COMPLETION DATE)
| Project Name | Location | Developer | Capacity (Megawatts, Megawatt-hours) | Technology | Project Status | Estimated Commercial Operations | Tax Map Key(s) | PPA Price ($/kWh) | PUC Dockets | Information Links |
|---|---|---|---|---|---|---|---|---|---|---|
| O‘ahu | ||||||||||
| Mountain View Solar | Waianae | AES | 7 MW + 35 MWh Storage | Solar + Battery | PUC Approved; Constructing and Permitting | April 2026 | (1)8-5-003:031; (1)8-5-003:032; (1)8-5-019:035 | 0.1303 | 2020-0139 | Mountain View Solar |
| Waiawa Phase 2 Solar | Pearl City, Waipio Village | AES | 30 MW + 240 MWh Storage | Solar + Battery | PUC Approved; Constructing and Permitting | July 2026 | (1)9-6-004:024; (1)9-6-004:025; (1)9-6-004:026; (1)9-6-006:036 | 0.1242 | 2020-0137 | Waiawa Phase 2 Solar |
| Pu‘uloa Solar | Pearl Harbor | Ameresco | 6 MW + 30 MWh Storage | Solar + Battery | Project selected by utility, Negotiating | 2026 | (1) 1-1-10-066 | 0.215 | https://hpuc.my.site.com/cdms/s/puc-case/a2Gcs000003zrDlEAI/pc202401 | Pu‘uloa Solar |
| Pu‘uloa Energy | Pearl Harbor | Ameresco | 99 MW | Biofuel | Project selected by utility, Negotiating | 2027 | (1) 9-9-001-008 | To be announced | To be announced | Pu‘uloa Energy |
| Mahi Solar and Storage | Kunia | Longroad Energy | 120 MW + 480 MWh Storage | Solar + Battery | Under PUC Review | 2026 | (1) 9-2-004-010; (1) 9-2-004-003; (1) 9-2-004-006; (1) 9-2-004-012 | 0.2306 | 2025-0414 | Mahi Solar and Storage |
| Kalaeloa Partners Combined Cycle Repower | Kapolei | Kalaeloa Partners | 208 MW | Biofuel | Project selected by utility, Negotiating | 2033 | (1)9-1-031:023 | To be announced | To be announced | Base proposal |
| Waiau Repower | Pearl City | Hawaiian Electric | 253 MW | Biofuel | Under PUC Review | 2033 | (1)9-8-003:010; (1)9-8-004:003 | Self build project | 2017-0352 | Waiau Repower |
| Maui Nui | ||||||||||
| Kaheawa Wind 1 (repower) | Ma‘alaea | Terraform US | 30 MW | Wind | Project selected by utility, Negotiating | 2026 | 8-001-001-6001; 3-6-001-014-6001 | To be announced | To be announced | Kaheawa Wind 1 |
| Pulehu Solar & Storage | Pulehu | Longroad Energy | 20 MW + 80 MWh Storage | Solar + Battery | Project selected by utility, Negotiating | 2027 | (2)2-5-001-003 | To be announced | To be announced | Pulehu Solar & Storage |
| Kuihelani Solar Phase 2 | Ma‘alaea | AES | 40 MW + 160 MWh Storage | Solar + Battery | Project selected by utility, Negotiating | 2027 | (2)3-8-005-002 | To be announced | To be announced | Kuihelani Solar Phase 2 |
| ‘Ūkiu Energy | Puunene | Ameresco, Inc. | 40 MW | Biofuel | PPA filed; Docket suspended for environmental review | 2027 | (2) 3-8-003:024 | Under negotiation | 2025-0356 | ‘Ūkiu Energy |
| Waena Battery Energy Storage | Kahului | Hawaiian Electric Company, Inc. | 40 MW / 160 MWh | Battery | PUC Approved; Permitting | April 2027 | (2)3-8-003:023 | Self build project | 2020-0132 | Waena Project Summary HE Self-Build Projects |
| Hawai‘i Island | ||||||||||
| Hamakua Firm Renewable Energy | Honoka’a | Pacific Current | 60 MW + 30 MWh Storage | Combined Cycle + Battery | Project selected by utility, Negotiating | 2030 | (3) 4-5-002-056; (3) 4-5-002-057 | To be announced | To be announced | Hamakua Firm Renewable Energy |
| Keamuku Solar | Waikoloa Village | AES | 86 MW + 344 MWh Storage | Solar + Battery | Project selected by utility, Negotiating | 2030 | (3) 6-8-002-008; (3) 6-8-002-010 | To be announced | To be announced | Keamuku Solar |
| Kaua‘i | ||||||||||
| Māna Solar & Storage | Kekaha | AES | 35 MW + 140 MWh Storage | Solar + Battery | PPA Filed, Under PUC Review | 2028 | (4) 1-2-002:001 | 0.127 | 2025-0191 | Mana Solar & Storage |
| Kaawanui Solar & Storage | Pakala Village | AES | 43 MW + 172 MWh Storage | Solar + Battery | PPA Filed, Under PUC Review | 2028 | (4) 1-7-006-010; (4) 1-7-006-006 | 0.1334 | 2025-0198 | Kaawanui Solar & Storage |
Project information will be updated as information becomes publicly available.
implementing a utility-scale renewable energy project
Although each utility is different, typically the process begins with issuing a request for proposals (RFP) asking developers to submit bids to build a project and sell the energy to the utility. Developers scope out locations and develop cost estimates that conform to the utility’s requirements. The process is reviewed by the Public Utilities Commission through a quasi-judicial public forum. Selected bidders must sign a Power Purchase Agreement (PPA) that is reviewed in another public process prior to approval.
The Hawai‘i State Energy Office encourages developers, communities, and affected residents to begin working with each other when projects are in the early scoping phase rather than after a PPA has been executed. This allows communities and residents to contribute meaningfully to all aspects of the project’s development and gives developers the information they need to submit a successful bid and keep their project on schedule.
Utility Scale Project Development Process General Summary

The figure shows the general process for a project moving through the competitive bidding framework. It is important to note that the PUC approves both the utilities’ request for proposals (RFP), the guiding document for project selection, as well as the individual project PPAs. Projects that do not go through formal competitive bids generally start the process at step four.
The PUC docket process is an open forum that allows for public comment at any time in the proceeding. In addition, each project must obtain the requisite federal, state, and county permits and approvals, many of which offer the opportunity for public comment. HSEO’s Hawai‘i Statewide Energy Projects Directory and Hawaiian Electric’s Renewable Project Status Board provide additional information on these projects and other utility-scale projects now under development or construction, approved by the PUC, or awaiting PUC approval.
Hawaiian Electric Stage 3 Request for Proposals completed
The Hawaiian Electric Companies have filed RFPs with the Public Utilities Commission in Docket 2017-0352. More information is available on Hawaiian Electric’s Competitive Bidding Webpage. The RFP for O’ahu and Maui is combined and was approved by the PUC with conditions. Hawai’i Island has been approved by the PUC with conditions.


TWO ELECTRIC UTILITIES DELIVER POWER TO Hawai‘i RESIDENTS
Hawai‘i’s fossil fuel power plants have provided electricity to Hawai‘i residents for decades, but they are old, inefficient, and rely on internationally-sourced imported fuels subject to volatile energy markets. Hawaiian Electric and KIUC need a variety of renewable energy projects to replace these plants.
Each new utility-scale renewable energy project must be submitted to the PUC for review and decision. Some of these projects have been approved by the PUC, others are currently under review. An individual PUC docket has been created for each operational utility-scale renewable energy project listed on this website.
HAWAIIAN ELECTRIC COMPANY

Hawaiian Electric is procuring resources as it phases out fossil fuels towards achieving the goal of 100% renewable energy by 2045. Hawaiian Electric employs a comprehensive competitive bidding process for renewable energy procurement across its service territories on Oʻahu, Maui, and Hawaiʻi Island. This structured process involves developing Requests for Proposals (RFPs), selecting projects, and negotiating contracts, all under the oversight of the Public Utilities Commission.


KAUAI ISLAND UTILITY COOPERATIVE

KIUC projects are not subject to competitive procurement; however, projects seeking any power purchase agreement require approval from the PUC.